*) Hydrant 
  • Review Document ( Manual Book, Drawing Design, Single Line, Etc )
  • Visual Inspection ( Pipe Installation, Outdoor/Indoor Hydrant, Sprinkler, Pump, Panel Control, Etc )
* HYDRANT SISTEM INSTALASI JARINGAN UTAMA
1. Pipa Hisap
2. Pipa Utama
3. Pipa Cabang Utama
4. Pipa Cabang Lainnya
5. Kondisi Penampungan Air
6. Gate Valve
7. Check Valve
8. Kerangka Uji
9. Pompa Utama
10. Pompa Pacu
11. Pressure Swicth Pompa
12. Panel Listrik Pompa
13. Instalasi Listrik Pompa
14. Manometer Valve
15. Foot Valve
16. Pressure Release

* HYDRANT BOX/ ROL
1. Slang
2. Katup Pengeluaran
3. Kondisi cat 
4. Lampu Indikator

* HYDRANT PILAR
1. Kopling Pengeluaran 
2. Sambungan
3. Slang
4. Katup Pengeluaran

* SISTEM SPRINKLER
1. Pipa Utama  
2. Pipa cabang Utama
3. Kondisi penampungan air
4. Pedoman tekakan
5. Tingkap pengaman
6. Komponen Sprinkler
7. Pipa cabang lainnya
8. Kondisi valve
9. Kerangan uji

* SISTEM ALARM KONTROL PANEL
1. Indikator kelompok zona
2. Indikator zona alarm
3. Indikator kesalahan
4. Sakelar pengujian alarm
5. Sakelar pengujii battery
6. Sakelar sekat alarm
7. Catu daya (AC/DC)
8. Instalasi listrik alarm

* ALAT PEMADAM API (APAR)
1. Badan
2. Tabung / isi tabung
3. Nozzle /Mulut pancar
4. Las – lasan
5. Tutup bejana
6. Selang saluran pancar
7. Kunci/ segel pengaman
8. Manometer kontrol

  • Uji fungsi/ Funtion Test
==========